WUT Utility Vault Upgrades

Contract Number:
071347
Estimated Cost Range:
$685,000 to $750,000, plus Washington State Sales Tax (WSST)
Procurement Summary:
The Work required for this Project includes: Upgrading utility vaults in the drive aisle behind the pier at Washington United Terminal.
Work includes, sawcutting, removal of existing pavement or concrete on / around the vaults, replacement of frames and cover lids, installation of formwork / falsework and placement of reinforced concrete collar slabs around the cover lids.
Notes:
IMPORTANT- We had a issue with the Holders List, if you signed up please sign up again so that you get any updates that are posted. Specs posted 3.17.20, Holder's List posted 3.17.2020
BID DATE postponed, pre-bid will still be held-Addendum #1 posted 3.24.20, Addendum #2 posted 4.22.20, Addendum #3 posted 4.29.20. Holders List posted 5.4.20
NOTICE REGARDING PORT OF TACOMA INVITATION TO BID 071356-sealed bids must be received at the front desk of the Port Admin Office (1 Sitcum Plaza) on May 6th by 2:00pm PST. For the safety of our staff working in the building please wear masks when dropping off bids, posted 5.4.20, Bid Tab posted 5.7.20