Parcel 86 Bank Stabilization

Contract Number:
071513
Estimated Cost Range:
Estimated cost range is $113,000 to $130,000, plus Washington State Sales Tax (WSST).
Procurement Summary:
The Work required for this Project includes:
Installation of sheet pile bulkhead to stabilize select area of the upper bank of the Hylebos Creek above the mean higher high water (MHHW) mark. Work will include site regrading and restoration.
Notes:
QA#1 & Addenda #1 posted 8.23.21, pre-bid sign in sheet and agenda posted 8.25.21, Holders List posted 8.25.21, QA #2 posted 8.31.21, QA#3 posted 9.1.21, Addendum #2 posted 9.8.21, Preliminary Bid & Final Bid Tab posted 9.16.21
NOTE Bid opening date & time has been changed,