NIM Stormwater Pipe Extension

Contract Number:
071143
Estimated Cost Range:
Estimated cost range is $425,000 to $460,500, plus Washington State Sales Tax (WSST).
Procurement Summary:
The Work required for this Project includes: Installation of 785 feet of 24-inch drain pipe, storm drain manholes with concrete collars and connection to existing storm drain infrastructure.
Notes:
NOTE-Two pre-bids are scheduled 8/15 and 8/21 attendance is MANDATORY at one (1) of the pre-bids. Project Manual uploaded 8.8.19., Holders List posted 8.15.19, Pre-bid #1 sign-in sheet posted 8.15.29, QA #1 posted 8.19.19, Pre-bid #2 sign-in sheet posted 8.21.19, Addendum #1 posted 8.23.19, Bid Tab posted 9.5.19