Banana Yard Rail Switch Upgrade 2024

Contract Number:
071940
Estimated Cost Range:
Estimated cost range is $2,650,000 to $3,100,000, plus Washington State Sales Tax (WSST)
Procurement Summary:
The Port has been awarded U.S. Department of Transportation Federal Railroad Administration grant in the amount of $2,365,000. In which 58.55% will be applied towards this project.

The Work required for this Project includes but is not limited to: The removal and replacement of fifteen (15) No 9 turnouts; remove and dispose of existing ballast and placement of new ballast under turnouts; furnishing, lining, grading, and compaction of new turnouts and trackwork; removal and replacement of existing paved crossings; coordinate with the Port of Tacoma and Tacoma Rail to complete the work in a phased approach that limits impacts to track outages and traffic.
Notes:
Questions Due: February 29, 2024 @ 10:00 AM (PST)