Blair Terminal Fender System Upgrades
Blair Terminal Fender System Upgrades
Contract number:
071403
Estimated Cost Range:
Estimated cost range is $220,000 to $270,000, plus Washington State Sales Tax (WSST).
Contact:
Submit questions in writing, attention Heather Shadko.
Summary:
The Work required for this Project includes the removal and disposal of thirteen (13) timber fender piles, demolition and disposal of the timber wale and chock systems, rubber fenders and associated connection hardware. The Work shall include labor, equipment and incidental materials necessary to install Port-Furnished items including: thirteen (13) timber fender piles with Contractor furnished and installed rub facings, Port-Furnished steel wale system, and Port-Furnished stay chains. The contractor shall provide all labor, tools and materials necessary for stay chain installation as shown in the Drawings and described in the Specifications. The Work includes fresh heading two (2) timber fender piles.
Notes:
Pre-bid sign in sheet posted 10.29.20, QA #1 posted 11.2.20, QA #2 posted 11.4.20, Addendum #1 posted 11.4.20, Holders List posted 11.6.20, QA#2 revised. QA #3 posted 11.10.20, Bid tab posted 11.13.20
Bids due:
November 12, 2020 - 2:00pmPre-bid due:
October 29, 2020 - 12:00pmHolders list
Subscribe to the Holders List to receive all updates about this procurementDocuments
071403-201104.01 Blair Terminal Fender System Rehabilitation Proj Manual-Final.pdf
201104.01-Blair Installation Plans_BID SET FINAL-signed-rdcd.pdf
Blair Terminal Pier Repairs - Project No. 091415 (reference 1).pdf
Blair Waterway Terminal Container & Bulk Handling Facility Berth A & B (reference 2).pdf
071403 Pre-Bid Sign In Sheet_0.pdf
Blair Terminal Fenders 071403 QA #1-FINAL 11.2.20.pdf
Blair Terminal Fenders 071403 QA #2-FINAL 11.4.20.pdf
071403 Blair Terminal Fenders Addendum #1-FINAL 11.4.20.pdf
071403 Holder's List 11.6.20.pdf
Blair Terminal Fenders 071403 QA #2-Revised 11.6.20.pdf
071403 QA #3-FINAL 11.10.20.pdf
071403 Bid Tab-11.12.20-FINALpdf.pdf