Contract Number:
072141
Estimated Cost Range:
$700,000 to $1,000,000, plus Washington State Sales Tax (WSST).
Procurement Summary:
The Work required for this Project includes: Demolition of seven (7) building structures down to the foundation (foundations to remain per plan). Structures are a mixture of timber and steel framed buildings. Suitable materials must be recycled or reused as appropriate. Below grade utilities as indicated on the plans are to be capped and abandoned in-place.
Notes:
Estimated Start/End dates: June 1, 2025 – Dec 1, 2025
Site visit will be March 25 at 10AM
Site visit will be March 25 at 10AM
Bids Due:
Pre-Bid Conference and Site Tour:
Questions Due: