As part of the ongoing Taylor Way Rehabilitation project, crews will be replacing the rail crossings in the area.

Construction continues for the Taylor Way Rehabilitation project.

Beginning Sept. 21 and continuing through October, Taylor Way from East 11th Street to approximately 1,500 feet south (~1/2 way between E. 11th and Lincoln Avenue) will be closed to through traffic for roadway demolition and paving. Local access will be maintained. Detours are in place via Alexander Avenue.

Expect delays: On Sept. 9 and 10, from 8 a.m.

Expect delays: On Sept. 9 and 10, from 8 a.m. to 5 p.m., the Hylebos Bridge will be reduced to one lane, with flagger controlled alternating one-way traffic, for bridge testing. 

For approximately five weeks beginning Saturday, Aug.

We have received reports of drivers traveling down the wrong lanes on Taylor Way and then s

Construction began the week of July 7, 2020 and will be primarily focused on Taylor Way from E.

The City of Tacoma is scheduled to begin work on the Taylor Way Rehabilitation Project starting Tuesday, July 7, 2020. Work will primarily focus on Taylor Way from East 11th Street to State Route 509. Visit the project page for a current list of construction dates and activities.

Construction is expected to begin the week of July 7, 2020 (pending permits) and will be primarily focused on Taylor Way from E. 11th Street to SR 509. The work will generally include demolition, utility placement, rail crossing replacement and paving.  Tentative dates and activities include: