| Project stage | | Status |
| Design work | | Completed |
Included in the Puget Sound Regional Council's Transportation Improvement Program (TIP) | | Completed |
| NEPA/SEPA process | | Completed |
| Purchase of right of way | | Completed |
| Utility relocation | | Completed |
| Access roads for autos, East 19th and APM Terminals | | Completed |
| Constructing Lincoln Loop Road for truck access/queuing into APM Terminals and temporary access through the construction zone. | | Completed |
| Advertise bids for overpass | | Completed |
| Bid opening | | Completed |
| Contract award | | July 16, 2009 |
| Construction begins - Lincoln Avenue closed from Thorne Road to Milwaukee Way | | Sept. 8, 2009 |
| Grade separation roadraising event | | Sept. 18, 2009 |
| Under construction - Lincoln Avenue closed between Milwaukee Way and APM Road | | Sept. 28, 2009 |
| Under construction - Lincoln Avenue closed between Thorne Road and Marc Street (see detour map) | | Oct. 21, 2009 - present |
| Ribbon cutting to celebrate completed grade separation | | May 2011 |