Project schedule: Lincoln Avenue grade separation 

Image that shows which projects have been completed related to the Lincoln Avenue grade separation, and an illustration of the overpass.

Project stage Status
Design work Completed

Included in the Puget Sound Regional Council's Transportation Improvement Program (TIP)

 Completed
NEPA/SEPA process Completed
Purchase of right of way Completed
Utility relocation Completed
Access roads for autos, East 19th and APM Terminals Completed
Constructing Lincoln Loop Road for truck access/queuing into APM Terminals and temporary access through the construction zone. Completed
Advertise bids for overpass Completed
Bid opening Completed
Contract award July 16, 2009
Construction begins - Lincoln Avenue closed from Thorne Road to Milwaukee Way Sept. 8, 2009
Grade separation roadraising event Sept. 18, 2009
Under construction - Lincoln Avenue closed between Milwaukee Way and APM Road Sept. 28, 2009
Under construction - Lincoln Avenue closed between Thorne Road and Marc Street (see detour map) Oct. 21, 2009 - present
Ribbon cutting to celebrate completed grade separation May 2011

  * Highlighted section indicates the project's current status.